Current Projects

Stay up-to-date on the current projects happening in Cambridge. Current project status, schedule and budget can be viewed in the table below or click on one of the featured projects for detailed information.

Browse the map below for a complete list of current projects in Cambridge.

For a list of road closures around Cambridge, visit our road closures page.

Current project status

For any emergencies and/or urgent requests within the project boundary, please contact Infrastructure and Development at (519) 621-0740. If you have any questions or concerns regarding any of the projects listed below, please email the Project Management Office at pmo@cambridge.ca.

Name Map Status %Completed Schedule Budget Project Manager

Name Map Status %Completed Schedule Budget Project Manager
AT Design - Dan Spring Way Trail Delayed 3% Jan-27 to Dec-27 $100,000 Jason Leach
Avenue Rd MUT (Gail St to Franklin Blvd) Approved 0% Jan-26 to Dec-26 $83,200 Jason Leach
Hespeler Pedestrian Bridge Design In progress 7% Jan-27 to Dec-27 $521,200 Jason Leach
Hespeler Trail Project - Queen to Guelph Project work complete 80% Mar-21 to Dec-25 $183,849 Jason Leach
Multi-Use Trail - Dunbar Rd Phase 3 In progress 66% Dec-24 to Jun-26 $98,653 Deepak Manoj
Trail Bridge Design 2 In progress 5% Apr-26 to Apr-27 $147,400 Jason Leach
Trail Renewal - Northview Heights Trail Map Delayed 4% Feb-25 to Nov-27 $498,200 Jason Leach

Name Map Status %Completed Schedule Budget Project Manager
Cambridge Food Bank Approved 0% - $1,500,000
City-Wide Speed Limit Sign Implement In progress 90% Mar-24 to Dec-26 $288,256 Jason Leach
City-Wide Speed Limit Signage (2025) In progress 90% Dec-24 to Dec-26 $182,098 Jason Leach
Mountview & New Hope Columbarium Design In progress 15% Dec-24 to Oct-26 $90,000 Nathan Zrini
Old Mill Rd Traffic Calming In progress 70% Jan-22 to May-26 $168,000 Jason Leach
Placemaking Study and Pilot Project In progress 22% Mar-23 to Sep-26 $150,000 Alix Aitken
Public Art 50th Anniversary Project work complete 100% Mar-23 to Dec-25 $290,000 Shane Taylor
Sidewalk Installation - Edward Street (2 Delayed 4% Jul-24 to May-26 $75,000 Jason Leach

Name Map Status %Completed Schedule Budget Project Manager
Active Transportation Feasibility Review Approved 0% May-26 to Dec-26 $110,000 Jason Leach
Analysis City Owned Real Estate Assets Delayed 0% Mar-26 to Dec-26 $100,000 Michael Launslager
Assessing Infilling & Intensification Project work complete 100% Apr-15 to Dec-24 $467,580 John Matthew Blevins
Asset Management Plan - Phase 3 Project work complete 90% Nov-23 to Jul-26 $357,000 Johannes Krijnen
BIA Modernization In progress 75% Nov-24 to Apr-26 $100,000 Michael Launslager
Consulting Services - Planning Project work complete 99% Mar-21 to Dec-25 $97,486 Brandon Kent Demeester
Development Charges Update (2022) In progress 80% Jul-22 to Apr-26 $175,642 Katherine Hyde
Galt Connected - Mobility and Streets Approved 0% Jan-26 to Dec-26 $400,000 Jason Leach
Galt Core Heritage Conservation District In progress 80% Oct-20 to Jun-26 $161,078 Laura Waldie
Galt Special Policy Area Review Approved 0% Sep-26 to Jul-28 $275,000 Melissa Castellan Aldunate
HAF Additional Res Unit Assistance Prog. Project work complete 99% Mar-24 to Dec-26 $1,563,400 Laura Dewar
HAF Affordable Housing CIP In progress 90% Mar-24 to Apr-26 $845,000 John Matthew Blevins
HAF Delegation of Authority Enhancements Project work complete 100% Mar-24 to Dec-25 $281,400 Laura Dewar
HAF Form Based Zoning By-Law In progress 100% Jun-24 to Apr-26 $570,800 Bryan Cooper
HAF Housing Needs Assessment & Strategy Project work complete 100% Mar-23 to Jan-26 $420,100 John Matthew Blevins
HAF Strategic Growth Area Secondary Plan In progress 75% Mar-24 to Dec-26 $366,500 John Matthew Blevins
HAFMunicipal Land for Affordable Housing In progress 85% Jun-24 to Dec-26 $5,038,735 John Matthew Blevins
Heritage Conserv District Study Hespeler In progress 97% Mar-23 to Sep-26 $100,000 Jeremy Edward Daniel Parsons
Heritage Property Designations (OHA) In progress 76% Mar-24 to Dec-26 $403,800 Nick R Borcescu
Heritage Register Review In progress 40% Mar-24 to Apr-26 $250,000 Nick R Borcescu
Hespeler Transportation Assessment In progress 3% Mar-24 to Jul-26 $150,000 Irum Sanaullah
Inclusionary Zoning In progress 75% Jan-23 to Mar-27 $125,000 John Matthew Blevins
Library Facilities Master Plan Project work complete 100% Dec-24 to Mar-26 $90,000 Mirna Raponi
Northwest Hespeler Secondary Plan & MESP In progress 0% Mar-26 to Apr-27 $1,500,000 Sarah Austin
Official Plan Review In progress 0% Jan-26 to Dec-28 $325,000 Bryan Cooper
Older Adult Strategy In progress 81% Jan-22 to Apr-26 $76,000 Alix Aitken
Operations Facility Master Plan In progress 60% Apr-22 to Apr-26 $250,000 Michael Hausser
Preston Secondary Plan In progress 45% Dec-24 to Sep-26 $350,000 John Matthew Blevins
Rec Facility Sponsorship & Naming Plan In progress 55% May-22 to Dec-26 $150,000 Shane Taylor
Recreation Facilities Action Plan - Ph 1 Delayed 0% Dec-24 to Dec-26 $100,000 Meghan Hunter
Recreation Services Rates & Fees Review In progress 5% Sep-24 to Dec-26 $75,000 Nicole Cichello
Residential Parking Bylaw Review In progress 7% Mar-21 to Jul-26 $80,000 Christine Kinahan
River Road Area - Class EA In progress 70% Mar-23 to Jun-26 $200,000 Sarah Austin
Road Safety Audits In progress 5% Dec-24 to Sep-26 $120,000 Christine Kinahan
Road Safety Review & Action Plan (2025) In progress 2% Dec-24 to Jul-27 $200,000 Christine Kinahan
Saginaw Parkway at Green Vista Drive Int In progress 50% Jun-26 $100,000 Kyle Novak
Sanitary Sewer Model Update (2022) In progress 95% Jan-22 to Jun-26 $250,000 Sarah Austin
Stormwater Technical Study Delayed 1% Mar-22 to Mar-27 $275,000 Sarah Austin
Strategic Plan Approved 0% Jan-26 to Dec-28 $165,600 Jenna Brown-Jowett
SWM Funding Study - Implementation Plan In progress 95% Jul-22 to Apr-26 $200,000 Sheena Pawliwec

Name Map Status %Completed Schedule Budget Project Manager
Heritage Condition Assessment – Phase 2 In progress 90% Mar-23 to Apr-26 $242,100 Ellise Paltser
SWM Pond Condition Assessments In progress 80% Dec-24 to Feb-29 $123,000 Andrew Schenk

Name Map Status %Completed Schedule Budget Project Manager
Corydon Pump Station Upgrade – Design In progress 55% Jan-23 to Jun-26 $100,000 Scott Murray Macdonald

Name Map Status %Completed Schedule Budget Project Manager
Energy Mgmt - Corporate Buildings In progress 40% Dec-24 to Mar-27 $150,000 Ryan Hoeksma
Region - 188 Water St In progress 5% Dec-24 to Jan-28 $110,000 Sarah Austin
SWM Pond Fence Repairs Map In progress 80% Nov-25 to Apr-26 $100,000 Prasad Samarakoon

Name Map Status %Completed Schedule Budget Project Manager
Bunker Gear (New Personnel) Year 1 In progress 10% Sep-26 to Dec-26 $100,000 Brad Michael Churchill
Bunker Gear Phase 2 In progress 95% Dec-24 to Apr-26 $264,000 Brad Michael Churchill
Equipment Growth In progress 38% Feb-26 to Feb-29 $529,200 Garth Buttenham
Equipment Growth (2024) In progress 61% Mar-24 to Dec-26 $326,600 Garth Buttenham
Equipment Growth (2025) In progress 43% Dec-24 to Dec-26 $816,500 Garth Buttenham
Equipment Replacement In progress 10% Feb-26 to Feb-29 $4,190,000 Garth Buttenham
Equipment Replacement (2023) In progress 94% Mar-23 to May-26 $2,954,478 Michael Hewlett
Equipment Replacement (2024) In progress 96% Jan-24 to Apr-26 $4,170,000 Garth Buttenham
Equipment Replacement (2025) In progress 51% Dec-24 to Dec-26 $4,111,000 Garth Buttenham
Fire Fighting Equipment Phase 1 In progress 95% Dec-24 to Apr-26 $64,900 Brad Michael Churchill
Fire Fighting Equipment Phase 2 In progress 5% Jan-26 to Dec-26 $71,400 Brad Michael Churchill
Fire Fleet Apparatus (2024) - Pumper In progress 60% Feb-23 to Jul-26 $1,322,900 Brad Michael Churchill
Fire Fleet Apparatus (2025) - Rescue In progress 20% Dec-23 to Jul-27 $1,579,845 Brad Michael Churchill
Fire Fleet Apparatus (2029) In progress 20% Nov-29 $2,392,000 Brad Michael Churchill
Fire Fleet Growth (2025) In progress 40% Jan-25 to May-29 $1,535,311 Brad Michael Churchill
Fleet Hoist Replacement In progress 10% Feb-26 to Feb-27 $101,800 Garth Buttenham
Laptop/Desktop Replacement Lifecycle In progress 0% Jan-26 to Dec-26 $286,000 Harshvardhansinh J Mahida
Library Computer Equipment In progress 0% Jan-26 to Dec-26 $75,500 Mirna Raponi
Library Computer Equipment (2024) Project work complete 100% Jan-24 to Mar-26 $453,000 Mirna Raponi
Library Materials In progress 30% Jan-26 to Sep-26 $109,000 Mirna Raponi
Light Fire Fleet In progress 20% Jan-26 to Dec-26 $166,400 Brad Michael Churchill
Public Safety Equipment Phase 1 In progress 90% Dec-24 to Apr-26 $76,000 Damond Jamieson
Public Safety Equipment Phase 2 In progress 0% Jan-26 to Dec-26 $64,500 Damond Jamieson

Name Map Status %Completed Schedule Budget Project Manager
1300 Bishop - Washrooms/HVAC Approved 0% Jan-26 to Dec-26 $254,300 Ryan Hoeksma
19 Cambridge Renovation Map In progress 11% Dec-24 to Dec-26 $202,000 Steven Ruffini
Allan Reuter - Exterior Steps/Guardrail In progress 0% Mar-26 to Dec-26 $73,700 Slobodanka Lekic
Arena Elevator Replacements In progress 80% Sep-24 to Jul-27 $1,500,000 Slobodanka Lekic
Arena Safety Netting Delayed 0% Dec-24 to Dec-26 $175,000 Olu Ojikutu
BOC - Concrete Floor Drainage Upgrades Approved 0% Jan-26 to Jun-27 $1,234,400 Steven Ruffini
Boiler Replacement (Old Post Office) In progress 5% Jan-26 to Sep-26 $60,000 Mirna Raponi
City Hall - Elevator Accessibility Approved 0% Jan-26 to Dec-26 $101,800 Meghan Hunter
City Hall Campus Revitalization Phase 1 In progress 0% Jan-26 to Dec-26 $300,000 Nathan Zrini
Corporate Facilities - Design Approved 0% Feb-26 to Jun-27 $305,300 Slobodanka Lekic
Duncan McIntosh Arena - Sitework Approved 0% Jan-26 to Dec-26 $50,000 Juan David Henao Lopez
Energy Management - Corporate Buildings In progress 0% Jan-26 to Dec-26 $1,413,400 Ryan Hoeksma
Entrance Accessibility (Old Post Office) In progress 5% Jan-26 to Dec-26 $101,000 Mirna Raponi
Ferguson Homestead Heritage Restoration Map In progress 14% Dec-24 to Dec-26 $244,000 Juan David Henao Lopez
Fire Station 1 Kitchen Map In progress 0% Dec-24 to Jun-26 $135,000 Steven Ruffini
Fire Station 1 Lunchroom and Lounge Approved 0% Jan-26 to Dec-26 $162,800 Steven Ruffini
Fire Station 1 Washroom Approved 0% Jan-26 to Dec-26 $234,700 Ryan Hoeksma
Fire Station 4 Expansion Design In progress 1% Dec-24 to Jun-27 $228,800 Steven Ruffini
Fire Station 5 Sewer Pipe In progress 22% Dec-22 to Dec-26 $120,000 Juan David Henao Lopez
Fire Station 5 Windows and Doors Approved 0% Jan-26 to Dec-26 $153,200 Steven Ruffini
Galt Arena Roof Window Replacement Map In progress 12% Dec-24 to Jun-26 $273,700 Steven Ruffini
Glass Railing Replacement (Hespeler) In progress 5% Jan-26 to Dec-26 $202,000 Mirna Raponi
Heritage Reno - Exterior Market Building Map In progress 16% Nov-25 to Mar-27 $848,400 Juan David Henao Lopez
Heritage Reno – H. Town Ctr & F. Market In progress 65% May-24 to Dec-26 $300,000 Juan David Henao Lopez
Hespeler Arena Dehumidifiers In progress 91% Mar-23 to Jun-26 $1,045,400 Slobodanka Lekic
Johnson Ctr - Skylight, Window & Lights Map In progress 6% Dec-24 to Jun-26 $287,900 Steven Ruffini
Library - Bldg Envelope Repair (Preston) Project work complete 100% Jan-22 to Jun-24 $367,800 Mirna Raponi
Library Atria Revit. (Queen's Square) Map In progress 60% Dec-24 to Jun-27 $252,500 Mirna Raponi
Library Elevator Modernization Hespeler Map In progress 25% Dec-24 to Dec-26 $176,800 Mirna Raponi
Library HVAC Replace (Queen's Square) Project work complete 100% Jan-24 to Jan-26 $86,000 Mirna Raponi
Library HVAC Replacement (Preston) In progress 10% Jan-24 to Dec-26 $245,000 Mirna Raponi
Library HVAC Replacement Queen Square In progress 10% Jan-26 to Nov-26 $277,800 Mirna Raponi
Library Queens Sq Entrance Renovations In progress 5% Dec-21 to Dec-26 $120,000 Mirna Raponi
Library Roof Replace - Preston Project work complete 100% Nov-23 to Mar-26 $696,900 Mirna Raponi
Library Roof Replace - Queen Square (92) Project work complete 100% Jul-24 to Mar-26 $418,000 Mirna Raponi
Lutz House Heritage Restoration Map In progress 18% Dec-24 to Jun-26 $152,000 Juan David Henao Lopez
Mountview Maintenance - Roof Replace Approved 0% Jan-26 to Dec-26 $65,100 Slobodanka Lekic
Parklawn Cemetary Roof Replacement Map In progress 95% Dec-24 to May-26 $84,400 Ryan Hoeksma
Preston Auditorium - Design Project work complete 95% Jan-20 to Dec-25 $1,954,474 Shane Taylor
Preston Scout House Heritage Restore Map In progress 37% Dec-24 to Dec-26 $20,448 Juan David Henao Lopez
Riverside Water Building Roof Replace Map In progress 90% Dec-24 to Jun-26 $267,800 Ryan Hoeksma
Roof Replace - Durward Centre In progress 0% Jan-26 to Dec-26 $525,200 Steven Ruffini
WG Johnson - Family Washroom Renovation In progress 0% Jan-26 to Dec-26 $295,000 Slobodanka Lekic
WG Johnson Pool Amenity In progress 0% Jan-26 to Dec-26 $156,000 Meghan Hunter

Name Map Status %Completed Schedule Budget Project Manager
17 Cambridge - Electrical EV Chargers Approved 0% Jan-26 to Dec-26 $132,300 Ryan Hoeksma
East side EW and NS Collector Rd Design Project work complete 99% Sep-18 to Jun-26 $1,800,500 Alex Darrell Nichols
East Side EW Collector Rd Map Delayed 0% Mar-26 to Mar-28 $750,000 Alex Darrell Nichols
East Side Middle Block Rd Approved 0% Apr-26 to Nov-27 $6,921,200 Alex Darrell Nichols
East Side NS Collector Rd Map In progress 90% Jul-23 to Sep-27 $8,103,000 Alex Darrell Nichols
ES Middle Block Rd (Fountain to NS Rd) In progress 30% Mar-25 to Dec-26 $670,700 Alex Darrell Nichols
ES Speedsville Infrastructure Design Delayed 0% Dec-24 to Jul-27 $487,100 Sarah Austin
EV Charging Stations In progress 10% Feb-26 to Feb-27 $91,600 Garth Buttenham
Forbes Dovecote at Jacobs Landing In progress 0% Apr-26 to Nov-27 $420,200 Jeremy Edward Daniel Parsons
Future Planned Roundabout Delayed 0% Jan-26 to Dec-26 $500,000 Neil Lacey
Limerick Road Design Delayed 0% Sep-25 to Sep-26 $202,500 Alex Darrell Nichols
N Camb Railway Grade Separation Delayed 0% Oct-21 to Nov-27 $19,306,500 Sarah Austin
New Street Light Installations In progress 20% Mar-26 to Dec-26 $88,400 Jason Leach
Pedestrian Crossings Approved 0% Jan-26 to Sep-26 $220,000 Jason Leach
Region - Fountain St N Design In progress 0% Feb-26 to Jan-27 $191,300 Alex Darrell Nichols
SE Galt Upper Greengate/LVH Moffat Creek Map In progress 55% Aug-22 to Dec-26 $615,000 Sarah Austin
Traffic Calming Implementation In progress 0% Jan-26 to Dec-26 $400,000 Christine Kinahan
Water Meter Growth In progress 0% Jan-26 to Dec-26 $300,000 Jason Alexander
West River Road Trunk Sanitary Access Map In progress 50% Jan-26 to Dec-27 $1,310,000 Scott Murray Macdonald

Name Map Status %Completed Schedule Budget Project Manager
Land Acquisition 1 - Confidential Map Delayed 90% Mar-19 to Apr-26 $3,975,000 Neil Lacey
Utility Easement Acquisition (2023) In progress 80% Mar-23 to Apr-26 $150,000 Neil Lacey

Name Map Status %Completed Schedule Budget Project Manager
Network Eq. Lifecycle/Replace 2024 In progress 60% Mar-24 to Dec-26 $400,000 Hristo Nikolov

Name Map Status %Completed Schedule Budget Project Manager
HAF Development Guide & Portals Project work complete 100% Jun-24 to Jan-25 $364,600 Tanya Gies
HAF Digital Twin Accelerated Approvals In progress 27% Jun-24 to Sep-26 $3,896,400 Kirby Childerhose

Name Map Status %Completed Schedule Budget Project Manager
Accessible Ball Diamond - Design In progress 85% Mar-24 to Dec-26 $150,000 Nathan Zrini
Recreation Complex - Construction In progress 30% Mar-24 to Dec-27 $105,536,600 Shane Taylor
Recreation Complex - Design In progress 90% Jan-20 to Dec-26 $6,437,020 Shane Taylor

Name Map Status %Completed Schedule Budget Project Manager
Accessible Ball Diamond - Construction Map In progress 15% Dec-24 to Feb-27 $3,025,000 Nathan Zrini
Cam West Bismark Park South Delayed 0% Feb-26 to Sep-27 $390,000 Vicki Armitage
Cambridge Dog Park Design Delayed 0% Jan-27 to Dec-27 $100,000 Nathan Zrini
Cricket Feasibility Study In progress 25% Mar-24 to Apr-26 $41,315 Michael Hausser
Fountain Soccer Netting In progress 2% Apr-26 to Dec-26 $231,100 John Paul Bartle
Hespeler Skate Park Design In progress 5% Dec-24 to Dec-27 $110,000 Nathan Zrini
Jumpstart Accessible Sports Amenity Cons In progress 85% Oct-24 to Jun-27 $961,641 Vicki Armitage
Land Acquisition - Confidential 3 In progress 0% Dec-24 to Oct-26 $4,255,000 Neil Lacey
Lions Can Amera Splashpad Design/Build In progress 50% Feb-24 to Sep-26 $860,000 Nathan Zrini
Park Dev - Treasure Hill Map Delayed 0% Apr-27 to Oct-28 $677,800 Vicki Armitage
Park Dev - Wesley Blvd Community Park In progress 3% Feb-26 to Nov-26 $1,248,000 Shane Taylor
Park Dev Isherwood Design Delayed 2% Jan-26 to Sep-27 $51,000 Vicki Armitage
Park Dev Lakeview/Morrison Design Delayed 2% Feb-26 to Oct-27 $71,700 Vicki Armitage
Park Dev Saginaw Subdivision Delayed 2% Jul-24 to Nov-26 $235,000 Vicki Armitage
Soper Park Outdoor Pool Design and Plan In progress 75% Mar-24 to Dec-28 $425,000 Steven Ruffini
Soper Park Plan In progress 5% Dec-25 to Dec-26 $25,000 Nathan Zrini
Trail Dev - Cambridge West Map In progress 96% Sep-23 to Sep-26 $679,400 Vicki Armitage
Trail Dev - South Point Ph 2 (Bosdale) In progress 10% Apr-26 to Oct-27 $356,700 Vicki Armitage
Trail Dev - Treasure Hill Map In progress 75% Dec-24 to May-28 $634,000 Vicki Armitage

Name Map Status %Completed Schedule Budget Project Manager
Basketball Refurb - Churchill & Weaver Map In progress 15% Dec-24 to Feb-27 $400,000 Nathan Zrini
Churchill & Birkinshaw Path Lighting In progress 5% Dec-24 to Jun-26 $90,000 Nathan Zrini
Churchill Picnic Pavillion/Pond Design In progress 0% Dec-24 to Dec-26 $119,000 Nathan Zrini
Playground Replace - Hespeler Optimist In progress 0% Jan-26 to Oct-26 $528,600 Nathan Zrini
Playground Replacement - Forbes Park Map In progress 0% Apr-26 to Aug-26 $669,100 Nathan Zrini
Playground Replacement - Hill 60 Park Map In progress 0% Mar-26 to Nov-26 $210,100 Nathan Zrini
Playground Replacement - Willard Park Map In progress 0% Apr-26 to Jul-26 $630,200 Nathan Zrini
Riverside Park Heritage Gates Design Approved 0% Mar-26 to Dec-26 $62,400 Nathan Zrini

Name Map Status %Completed Schedule Budget Project Manager
Black Bridge Road and Bridge, Design In progress 99% May-18 to Jun-26 $1,660,669 Scott Murray Macdonald
Blackbridge and Townline Road Utility Project work complete 99% Mar-23 to Feb-26 $331,000 Scott Murray Macdonald
Blair Road Retaining Wall Construction Map In progress 1% Jan-26 to Dec-26 $1,800,000 Matt Holland
Cooper Street Reconstruction In progress 0% Jan-26 to Dec-27 $3,890,000 Matt Holland
Cooper Street Reconstruction (2025) Map In progress 45% Dec-24 to Jan-28 $4,494,894 Matt Holland
Dayton St. Reconstruction Map In progress 2% Jan-26 to Nov-27 $1,964,000 Scott Murray Macdonald
Elgin St N (Glamis to CP Rail) Phase 1 Map In progress 0% Jan-26 to Dec-27 $12,515,000 Jackeline Benato
Henry, Serviss and McAuslan St Recon Map In progress 11% Jan-26 to Dec-27 $4,305,000 Deepak Manoj
Infrastructure Design In progress 5% Jan-26 to Dec-27 $1,000,000 Jamie Croft
Infrastructure Design (2023) In progress 70% Jan-23 to Jun-26 $521,000 Jamie Croft
Infrastructure Design (2025) In progress 20% Jan-25 to Dec-27 $820,000 Jamie Croft
Keffer St. and Laneway 13 Rehabilitation Map In progress 14% Jan-26 to Dec-26 $1,000,000 Kyle Novak
Moore St and Hamilton St Reconstruction Map In progress 0% Apr-26 to Dec-27 $3,700,000 Andrew Schenk
Queen Street West Reconstruction Map In progress 2% Dec-24 to Jan-28 $3,200,000 Matt Holland
Ramore St and Gilholm Ave Reconstruction Map In progress 14% Apr-26 to Dec-27 $2,284,000 Kyle Novak
Region - Water St (Ainslie to Simcoe St) Map Delayed 10% Jan-22 to Nov-26 $780,000 Sarah Austin
Riverside Dam Detailed Design In progress 98% Mar-23 to Jun-26 $525,000 Scott Murray Macdonald
Saginaw at Green Vista Dr Intersection Approved 0% Apr-26 to Dec-27 $884,000 Jason Leach
Townline Road Reconstruction Map In progress 0% Jan-26 to Nov-28 $12,064,000 Scott Murray Macdonald
Watermain Decom Design Along Grand River Project work complete 100% Feb-23 to Feb-26 $155,962 Scott Murray Macdonald

Name Map Status %Completed Schedule Budget Project Manager
Asphalt Resurfacing Program Map In progress 5% Apr-26 to Jul-27 $1,600,000 Brandon Kent Demeester
Blackbridge Rd and Bridge Reconstruction Map In progress 25% May-24 to Oct-27 $20,600,000 Scott Murray Macdonald
Bridge & Culvert Design In progress 80% Mar-24 to Sep-26 $250,000 Jamie Croft
Bulk Fill Station Replacement In progress 0% May-26 to Aug-26 $100,000 Jessie L Koczynasz
Burnett Sanitary Sewer and Manhole Recon In progress 8% Jul-26 to Jul-27 $150,000 Kyle Novak
Elgin Street North Utility Relocations In progress 50% Mar-24 to Aug-26 $300,000 Jackeline Benato
Entry Sign Replacement Approved 0% Jan-26 to Jun-27 $50,000 Alana Russell
Fire Station 1 - Training Tower Tiles Approved 0% Jan-26 to Dec-26 $122,100 Steven Ruffini
Hespeler Arena - Pumping Equipment Approved 0% Apr-26 to Dec-26 $54,000 Ryan Hoeksma
Infrastructure Design (2024) In progress 80% Sep-24 to Dec-26 $536,000 Jamie Croft
Jacobs Landing Flood Wall Repair In progress 8% Jul-26 to Jul-27 $150,000 Kyle Novak
Laneway Renewal Program Map In progress 5% May-26 to Dec-26 $1,465,000 Andrew Schenk
Newland Pool Walkway Improvements In progress 25% - $175,000 Andrew Schenk
Parking Lot - Westminster & Water St N Map Delayed 0% Jan-26 to Dec-26 $53,000 Jason Leach
Pedestrian Bridges Deck Replacements In progress 50% Mar-23 to Dec-26 $216,000 John Paul Bartle
Riverside Artesian Well Outlet Changes In progress 33% Dec-24 to Jul-27 $68,000 Andrew Schenk
Riverside Dam Repair Map In progress 68% Dec-24 to Dec-26 $425,000 Scott Murray Macdonald
Riverside Dam Safety Improvements In progress 0% Mar-26 to Nov-27 $200,000 Scott Murray Macdonald
SCADA System Review Approved 0% Jan-26 to Dec-26 $100,000 Jason Alexander
Sewer Lining Citywide Map In progress 8% Jan-26 to Dec-26 $2,400,000 Jackeline Benato
Siphon Operation Procedures Approved 0% Jan-26 to Jun-27 $100,000 Robert James Black
Snow Storage Facility Design & Permits In progress 0% May-26 to Dec-27 $171,600 Jackeline Benato
Storm Pond Design In progress 0% Jan-26 to Dec-26 $140,000 Andrew Schenk
W River Rd Trunk Sanitary Access- Design In progress 61% Apr-24 to Oct-26 $90,000 Scott Murray Macdonald
Water Meter Replacement Program In progress 2% Jan-26 to Dec-26 $1,032,300 Harpreet Singh Sumra
Watermain Decomm. Along Grand River Map In progress 2% Jul-26 to Oct-27 $1,100,000 Scott Murray Macdonald
Watermain Lining Citywide Map In progress 11% Jan-26 to Dec-27 $4,950,000 Deepak Manoj
Watermain Lining Rehabilitation Design In progress 90% Dec-24 to Jul-27 $172,728 Deepak Manoj
WG Johnson - Building Automation Systems In progress 0% Jan-26 to Dec-26 $123,300 Ryan Hoeksma
Witmer Pumping Station - Construction Approved 0% Feb-26 to Dec-28 $1,560,000 Robert James Black
Witmer Pumping Station Upgrade- Design In progress 15% Dec-24 to Sep-27 $291,909 Robert James Black

Name Map Status %Completed Schedule Budget Project Manager
Cloud Strategy Implementation - Phase 2 Approved 0% Jan-26 to Dec-26 $200,000 Hristo Nikolov
Migration of Integrations to Cloud Approved 0% Jan-26 to Dec-26 $500,000 Wei Li Wang

Name Map Status %Completed Schedule Budget Project Manager
Communitech Partnership Delayed 11% Dec-24 to Dec-26 $50,000 Karisa Downey
Records and Information Management Project work complete 100% Mar-24 to Dec-25 $130,253 Veronica Mary Carr

Name Map Status %Completed Schedule Budget Project Manager
ActiveNet Roadmap Implementation (2024) In progress 20% Feb-25 to Dec-26 $150,000 Ahmed Kassad
ActiveNet Roadmap Implementation 2019 Project work complete 100% Mar-19 to Feb-26 $75,000 Ahmed Kassad
Amanda Roadmap Implementation In progress 95% Jan-22 to Apr-26 $450,000 Dianne Clare Glofcheskie
Amanda Roadmap Implementation (2023) In progress 20% Jan-23 to Sep-26 $250,000 Dianne Clare Glofcheskie
Amanda Roadmap Implementation (2024) Delayed 0% Mar-26 to Dec-27 $300,000 Dianne Clare Glofcheskie
BI/Business Data Warehouse Assessment Approved 0% Jan-26 to Dec-26 $100,000 Nikhilkumar Patel
BI/BW Strategy Development & Enhancement In progress 95% Jan-22 to Apr-26 $100,000 Nikhilkumar Patel
Camera and Security In progress 60% Jun-25 to Jun-26 $150,000 Rutvik Shah
cityONE (SAP) Enhancements Approved 0% Jan-26 to Dec-26 $208,000 Samir Desai
cityONE (SAP) Lifecycle Updates In progress 5% Jan-26 to Dec-26 $208,000 Samir Desai
cityONE (SAP) Lifecycle Updates (2025) In progress 55% Dec-24 to Jun-26 $200,000 Samir Desai
cityONE Lifecycle Enhancements (2025) In progress 10% Dec-24 to Jun-26 $200,000 Syed Murtaza
cityONE Lifecycle Updates & Replace 2024 Project work complete 100% Jan-24 to Jan-26 $500,000 Samir Desai
Cloud Strategy and Implementation In progress 15% Dec-24 to Dec-26 $100,000 Ryan Small
Connected City (2024) In progress 35% Mar-24 to Dec-26 $150,000 Syed Murtaza
Corporate Payment Sys Implementation Delayed 0% Jan-27 to Dec-27 $300,000 Revathi Devendran
Corporate Payment System Lifecycle In progress 10% Mar-25 to Dec-26 $400,000 Revathi Devendran
Customer Relationship Management In progress 25% Jan-23 to Dec-26 $228,884 Mohammad Mamun
Customer Relationship Mgmt Software Delayed 0% Aug-25 to Dec-26 $400,000 Mohammad Mamun
Database Middleware Integration/Process In progress 55% Jun-22 to Apr-26 $100,000 Ryan Small
Digital Transform Citizen Portal Enhance In progress 50% Sep-21 to Jun-26 $250,000 Helly Jayesh Shah
Disaster Recovery Site Enhancements In progress 5% Sep-25 to Jun-26 $300,000 Ryan Small
Fire Record Mgmt System Implementation In progress 5% Jan-26 to Dec-26 $250,000 Kirby Childerhose
GIS Roadmap Implementation (2024) In progress 35% Mar-24 to Dec-26 $350,000 Nicole Walker
GIS Roadmap Implementation (2025) In progress 5% Jan-26 to Dec-26 $100,000 Nicole Walker
Integration of Systems and Database In progress 15% Dec-24 to Dec-26 $250,000 Ryan Small
Laptop/Desktop Replacements (2025) Project work complete 100% Dec-24 to Oct-25 $250,000 Harshvardhansinh J Mahida
Library Computer Equipment (2025) In progress 95% Dec-24 to Apr-26 $271,200 Mirna Raponi
Parking Digitization and Service Enhance Approved 0% Jan-26 to Dec-26 $78,000 Syed Murtaza
Parking System & Process Digitization 24 In progress 45% Apr-25 to May-26 $100,000 Syed Murtaza
Renewal Capital Planning Support Tool In progress 48% Mar-23 to Dec-26 $250,000 Johannes Krijnen
Security Camera Hardware & App 2024 Project work complete 100% Mar-24 to Jan-26 $75,000 Rutvik Shah
SharePoint Roadmap Implementation Approved 0% Jan-26 to Dec-26 $70,600 Helly Jayesh Shah
SharePoint Roadmap Implementation (2024) In progress 90% May-25 to Apr-26 $100,000 Helly Jayesh Shah
Telephone Modernization - Teams 2024 In progress 95% Mar-24 to Apr-26 $300,000 Darren Hutchings
Website Renewal In progress 60% Dec-24 to Apr-26 $250,000 Alana Russell
Work Order Management System Enhance In progress 15% Jan-26 to Dec-26 $500,000 Jennifer Wrzala
Work Order Mgmt System Enhance 2024 In progress 40% Mar-24 to Jun-26 $350,000 Jennifer Wrzala